Town Park Recreation Centre
The Town Park Recreation Centre was constructed in 2002. The facility is host to our many of our recreation programs and activities, our Youth Centre, our various Day Camps, and the Agricultural Society’s Port Hope Fair.
View the our recreation fees and charges.

- Located at: 62 McCaul Street,
Port Hope, L1A 1L2 - Monday to Friday: 8:00 a.m. to 9:00 p.m.*
- Saturday and Sunday: 9:00 a.m. to 6:00 p.m.*
*Hours may vary depending on rentals and programming

Some of the amenities include:
- Cameco gymnasium
- Youth centre and lounge
- Multi-purpose rooms
- Skate Park
- Sports fields and tennis courts
Expansion of the Town Park Recreation Centre begins!
August 4, 2022
Construction is underway on the Town Park Recreation Centre Expansion Project! Work began the week of July 15, and progress so far is substantial. You will notice construction fencing has been erected around the area of work, and work on a temporary entrance is taking place. Programs continue to operate and access to the facility is not impacted. Read the news story about our recent ground-breaking ceremony.
August 22, 2022
Construction is moving along well on the Town Park Recreation Centre Expansion Project! Interior blockwork and tile work at the temporary entry door has been completed, and an accessible push button has been installed.
The pedestrian ramp up to the temporary entry at the south side of the building has been completed.
The building footprint has been excavated and granular stone has been placed on the base and compacted. Excavated materials are being removed from the site.
September 8, 2022
Dalren Inc. has completed all storm and sanitary work required for the new site and building. The pedestrian ramp up to the temporary door at the south side of the building is in operation. The new building strip footings have been poured and the forms stripped. The rebar was cast into the footings and is ready for the foundation walls.
Next, the foundation walls will be poured and masonry work can begin.
November 1, 2022
The new building footings have been completed and masonry is progressing well. Arrival of trusses and commencement of roofing are anticipated over the next two weeks. Floors are scheduled to be poured in early December. The building is starting to take shape!
January 6, 2023
Work continues on the Town Park Recreation Centre Expansion! The addition is really starting to take shape, with significant roof work and installation of windows.
January 16, 2023
A lot of progress on the Town Park Recreation Centre Expansion! Door frames, exterior doors, and interior windows have been installed, and exterior insulation is completed. The lower part of the roof over the vestibule and the lobby is complete as well!